Eskom Assures Another Full Day of Uninterrupted Power Supply

Eskom has extended uninterrupted electricity supply for its customers, originally planned for three days, now running until Tuesday afternoon. This extension is due to improved generation fleet performance and fully recovered emergency reserves.

Eskom Assures Another Full Day of Uninterrupted Power Supply

Starting on Tuesday at 4 pm until Wednesday at 5 am, Stage 1 load-shedding will be implemented

. Following this, load-shedding will be suspended from 5 am to 4 pm, only to resume Stage 1 load-shedding until 5 am on Thursday. This daily pattern will continue until further notice.

Eskom is dealing with breakdowns totaling 13,559MW, while planned maintenance affects 4,765MW of generation capacity.

The demand forecast for the evening peak stands at 25,054MW. Eskom will notify customers of any significant changes as necessary.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Eskom Media Today

Eskom Loadshedding will continue until 5:00 on Tuesday, as previously announced

Published

on

Eskom Loadshedding will continue until 5:00 on Tuesday, as previously announced

Until 05:00 on Tuesday, stage 4 loadshedding will continue. Until further notice, Stage 2 and 4 loadshedding will take place.

Eskom Loadshedding will continue until 5:00 on Tuesday, as previously announced

Monday, 10 July 2023: Stage 4 loadshedding is being implemented until 5:00 a.m. on Tuesday due to increased demand. On Wednesday, Stage 4 loadshedding will be implemented from 14:00 until 05:00, followed by Stage 2 loadshedding from 05:00 to 14:00.

Eskom Loadshedding Today

There will be a daily implementation of this pattern until further notice. A new update will be published if any significant changes are made.

As of now, 14 252MW of generating capacity has been damaged by breakdowns, while 4 118MW of generating capacity has been out of service for planned maintenance.

As of today, Duvha, Hendrina, Kendal, Kriel, Matimba and Medupi power stations have each reactivated a generating unit.

The Arnot and Tutuka power stations each had a generation unit out of service due to a breakdown during the same period.

Tutuka Power Station’s current capacity constraints are due to the delay in resuming two generating units. In order to restore service to the generating units, Eskom teams are working around the clock.

Members of the public are being encouraged to use electricity sparingly and efficiently, and we want to thank the people who do heed the call. During the period between 17:00 and 21:00, please turn off your geysers and pool pumps as this reduces demand, alleviates pressure on the power system, and contributes to fewer stages of load-shedding.